Progress Report : South Bank Quay, Teesworks

Doran Consulting is delighted to be the Lead Marine and Civils Designer of Phase 1 of the 1.2km heavy-lift quay, for GRAHAM Civil Engineering.

1 June 2022

See the progress made on the South Bank Quay project in the video below.

Doran Consulting is delighted to be the Lead Marine and Civils Designer of Phase 1 of the 1.2km heavy-lift quay, for GRAHAM Civil Engineering.

Installation of the 156No., 1.8m diameter, 28m long tubular piles is now complete with tie rod and waler beam installation progressing on the anchored combi wall. Once complete, the Works will facilitate river access to a 15-acre hardstanding and logistical space. The quay will be complete in spring 2023 to support SeAH Wind Ltd and GE Renewable Energy, playing a critical role in the loading and shipping of SeAH Wind’s monopile foundation structures and GE Renewable Energy’s 107m long turbine blades bound for the Dogger Bank wind farm.

Construction Progress South Bank Quay- Repost Teesworks

Latest News

Meeting the Next Generation of Engineers at Queen's University

Doran Consulting attended the Queen's University Belfast Careers Fair, meeting students and discussing graduate and year-out placement opportunities for 2027.

Read More

Belfast Grand Central Station Wins CEF Design Excellence Award

Doran Consulting and Arup have received the Design Excellence Award at the 2026 CEF Excellence Awards for Belfast Grand Central Station.

Read More

Success at the NI Active Travel Challenge Awards

Doran Consulting has been recognised at the Northern Ireland Active Travel Challenge Awards for logging the most journeys in the 100–499 employee category.

Read More

An Afternoon at Crumlin Road Gaol

Colleagues gathered at Crumlin Road Gaol for a staff event featuring project updates, new starters and a special celebration marking Sean Douglas's retirement after 38 years.

Read More